Preliminary studies have begun into opening a new rail line to serve a new station at Skelmersdale.

The old Skelmersdale Station - now long gone in the name of progress!

The old Skelmersdale Station – now long gone in the name of progress!

Lancashire County Council, Network Rail and Merseytravel are looking at the issues, which will continue through Network Rail’s GRIP Stage 3 (Governance for Railway Investment Projects, Option Selection).

Network Rail has advised Lancashire County Council that the GRIP3 work alone will cost as much as £4 million, and has suggested these key dates:

* GRIP3 concluded, January 2017.

* GRIP4 (Single options selection), to January 2019.

* GRIP6 (Construction, commissioning) April 2021 to April 2023.

* Train services start December 2023.